Only one of four Bengaluru suburban rail corridors has completed land acquisition

thehindu.com [$]

Only one of four Bengaluru Suburban Rail Project corridors has completed land acquisition, over four years after approval, delaying the ₹15,767-crore project. Corridor-2 (Mallige) is fully acquired with construction underway; Corridor-4 (Kanaka) has acquired only 7.8 of 57 acres. Expenditure so far is ₹2,659 crore, with delays blamed on private land and state land transfer issues. Corridors 1 and 3 have approved alignments with acquisition and utility shifting ongoing. No revised deadlines were given, though K-RIDE and Railways are coordinating to resolve problems.