OC Transpo to provide update on Trillium Line opening plans today

ottawa.ctvnews.ca October 31, 2024, 04:01 PM UTC

OC Transpo will provide an update today on the Trillium Line's opening. Transit Services general manager Renee Amilcar will discuss the completion of a 21-day trial running period and outline the next steps for the new O-Train line.

The trial included a 14-day simulation of passenger service and a week of testing staff responses to issues. The line, which runs from Bayview Station to Limebank Station with a spur to the airport, achieved a 99.5% on-time performance.

Amilcar previously indicated that final preparations will take three weeks, with the line expected to open to the public in mid-November.