Mumbai-Ahmedabad bullet train project resumes underground construction as tunnel boring machine arrives from China

zeenews.india.com

The Mumbai-Ahmedabad Bullet Train project is set to resume underground construction as a crucial tunnel-boring machine, delayed in China, is now en route to India. The massive Tunnel Boring Machine (TBM) is expected to arrive by September 24, with tunnelling operations scheduled to begin in January 2027, overcoming a significant foreign hurdle for the high-speed rail project. The TBM's shipment was previously held up following diplomatic discussions, and its arrival marks a major milestone for the ambitious project, which includes a 20.37-kilometer underground section.