leprogres.fr (French) —

Unit 3 of the Bugey nuclear power plant in Ain, France, has been shut down since November 21 for a scheduled partial inspection lasting about three months, according to EDF. Over 2,000 employees from EDF and around 40 contractor companies will carry out 13,000 maintenance, control, and modification operations, including checks on reactor core equipment, a full turbine inspection, and replacement of a 43-tonne primary pump motor. The work is part of the "Grand carénage" ten-year program to extend the plant's lifespan, with its phase B, focused on seismic and tornado resistance, scheduled for completion in 2029.