Ayodhya's Ram temple construction to finish by June 2025, says committee chairman

economictimes.indiatimes.com

The construction of the Shri Ram Janmabhoomi Temple in Ayodhya is set to be completed by June 2025. This includes finishing 85 murals, new titanium lattices, and a one-kilometer rampart. The rising tower is currently undergoing aviation safety checks. Construction Committee Chairman Nripendra Mishra stated that work on the ramparts and shoe racks will continue until September 2025. So far, 21 murals have been completed, and work on 60 others has begun. Mishra also mentioned plans to name four gates after respected saints from Ayodhya. The final inspection of statues will take place in Jaipur in early January, and digging for a central pool has started.